Skip to content

  • Home
  • COVID-19 Guide
  • COVID-19 AV library
  • Client results
  • Expertise
  • News & Insights
  • People
  • Our DNA
  • Inclusion and Diversity
  • Join us
  • Contact Us
Home / NEWS & INSIGHTS / Insight / Take-out won’t take away a right to payment
Insight 2 September 2020

Take-out won’t take away a right to payment

Parrwood Pty Ltd v Trinity Constructions (Aust) Pty Ltd [2020] NSWCA 172

The New South Wales Court of Appeal recently handed down its decision in Parrwood Pty Ltd v Trinity Constructions (Aust) Pty Ltd.[1]  The Court of Appeal upheld a finding at first instance that, where a reference date had arisen under the Building and Construction Industry Security of Payment Act 1999 (NSW) (Act), a claimant’s entitlement to payment was not suspended by the respondent subsequently issuing a notice to take works out of the claimant’s hand after that reference date had accrued.

The decision sought to clarify the seminal words of the High Court in Southern Han,[2] relating to the effect of suspension on reference dates under the Security of Payment legislation.  The decision also affirms the principle that a party is not able to take steps under a contract to ‘invalidate’ reference dates that have already accrued.

The decision supports the long-held principle that, absent a challenge to jurisdiction, an adjudicator must fulfil his or her function by making a determination.  An adjudicator cannot ‘decline’ to do so on the basis that a right to payment (as opposed to a reference date) has not yet arisen.

In light of the decision of Parrwood, principals and head contractors should be aware that where rights under the Act have accrued prior to take out action, a Contractor will be entitled to payment (subject of course to the merits of their claim).

Background

Parrwood Pty Ltd (Parrwood), as principal, and Trinity Constructions (Aust) Pty Ltd (Trinity Constructions), as contractor, were parties to a design and construct contract for a residential development.  Under the contract, Trinity Constructions was permitted to submit payment claims to be made on the 25th day of each month.

Following the accrual of the August 2019 reference date but prior to Trinity Constructions submitting a payment claim in respect of that date, Parrwood served a notice on Trinity Constructions taking the remaining works out of Trinity Constructions’ hands but not terminating the contract (Take-Out Notice). There was no dispute as to the validity of Parrwood doing so. Under the contract, the effect of the Take-Out Notice was that Trinity would be entitled to an ‘adjustment payment’ following the work being completed by another subcontractor.

Following the Take-Out Notice, Trinity Constructions issued a payment claim to Parrwood and then proceeded to adjudication (First Adjudication).

The adjudicator found that the amount owing to Trinity Constructions was ‘no amount’.  He did so on the basis that prior to service of the payment claim, Parrwood had taken the work out of Trinity Constructions’ hands and therefore, payment to Trinity Constructions could be suspended until its entitlements following the Take-Out Notice had been assessed by the Superintendent. The adjudicator made a number of statements in the determination, to the effect that he was ‘declining to make a determination’ on the basis that the payment claim was premature: that is, Trinity’s right to payment would not arise until the ‘adjustment payment’ was due.

Trinity Constructions subsequently withdrew the First Adjudication and made a new adjudication application. The second adjudicator found that:

(a) the adjudicator in the First Adjudication had failed to perform his statutory function because he had declined to determine the amount of the payment claim; and

(b) there was an amount owing to Trinity Constructions by Parrwood in respect of the payment claim,

(the Second Determination).

Parrwood then proceeded to Court to challenge the validity of the Second Determination.

The proceeding

The primary judge (Justice Ball) dismissed Parrwood’s summons and declared that the determination of the First Adjudication was null and void.[3]  In doing so, his Honour made the following observation with respect to the effect of contractual suspension on rights accruing under the Security of Payment legislation in light of the decision of Southern Han:

The point made by the High Court was that no reference date and no right to a progress payment could be pursued after suspension. It was not saying that no right could arise under the Act in respect of a right to a progress payment that arose before suspension. The right to make a payment claim in this case was such a right.

Parrwood subsequently appealed to the Court of Appeal.

The Court of Appeal found that the determination of the First Adjudication was vitiated by jurisdictional error as the adjudicator had failed to perform his function as prescribed by section 22(1)(a) of the Act.  The basis of the Court’s finding was that the adjudicator’s reasons made it plain that he did not determine the adjudicated amount on the basis that the Take-Out Notice had been served and therefore, concluded that ‘no amount’ was payable.

The Court subsequently went on to find that on and from 25 August 2019, being the date that a reference date had accrued under the Act, Trinity Constructions enjoyed a statutory entitlement to submit the payment claim, which it was entitled to do so for the succeeding 12 months.  This was notwithstanding that Parrwood had exercised its rights under the contract and served the Take-Out Notice, as the right to serve the payment claim had accrued prior to Parrwood doing so.

The Court of Appeal also found that as the determination of the First Adjudication was void, there was no obligation on Trinity Constructions to ‘approach a court’.  Therefore, it was not precluded from exercising its statutory right and making the second adjudication.[4]

For further information on the decision in Parrwood and related considerations for your project, please contact our Construction team below.

Special thanks to Cameron Baker for his assistance in putting this article together. 

[1] [2020] NSWCA 172.

[2] Southern Han Breakfast Point Pty Ltd (in liq) v Lewence Construction Pty Ltd (2016) 260 CLR 340 [2016] HCA 52.

[3] Parrwood Pty Ltd v Trinity Constructions (Aust) Pty Ltd [2020] NSWCA 172, [12].

[4] Ibid, [45].

This publication covers legal and technical issues in a general way. It is not designed to express opinions on specific cases. It is intended for information purposes only and should not be regarded as legal advice. Further advice should be obtained before taking action on any issue dealt with in this publication.

About the authors

  • Chris Nielsen

    Partner

In other news

New Industrial Relations Laws – What it means for you

22 December 2020Insight

Payment Times Reporting Scheme

21 December 2020Insight

Australian Government proposes new broadcaster’s licence and forced investment quotas in Media Reform Green Paper

14 December 2020Insight

Verification of identity – does it always need to be in person?

6 December 2020Insight

VIEW ALL NEWS & INSIGHTS

BRISBANE

Level 11, 66 Eagle Street
Brisbane QLD 4000
GPO Box 1855
Brisbane QLD 4001
Tel +61 7 3233 8888
Fax +61 7 3229 9949

 

GET IN TOUCH

Contact form

We handle your personal information in accordance with our privacy policy.

sydney

Level 32, MLC Centre
19 Martin Place
Sydney NSW 2000
GPO Box 462
Sydney NSW 2001

Tel +61 2 8241 5600
Fax +61 2 8241 5699

 

GET IN TOUCH

Contact form


We handle your personal information in accordance with our privacy policy.

melbourne

Level 27, 101 Collins Street
Melbourne VIC 3000
GPO Box 2924
Melbourne VIC 3001

Tel +61 3 9067 3100
Fax +61 3 9067 3199

 

GET IN TOUCH

Contact form

We handle your personal information in accordance with our privacy policy.

follow us

CLIENT LOGIN

newcastle

Level 2, 16 Telford Street
Newcastle NSW 2300
PO Box 394
Newcastle NSW 2300

Tel +61 2 4914 6900
Fax +61 2 4914 6999

 

GET IN TOUCH

Contact form


We handle your personal information in accordance with our privacy policy.

canberra

Level 9, 2 Phillip Law Street
Canberra ACT 2601

Tel +61 2 6243 3699
Fax +61 2 8241 5699

 

GET IN TOUCH

Contact form


We handle your personal information in accordance with our privacy policy.

© 2017 McCullough Robertson. Site map Disclaimer Privacy Policy Credit Reporting Policy

X